Bringing the World’s First Battery-electric Trolley Haulage System to Life
We visited Boliden’s Kristineberg mine in Sweden to see its new battery-electric trolley test track in action, and learn about the collaboration behind the breakthrough innovation

By Carly Leonida, European Editor



Boliden, Epiroc and ABB have taken the mining industry a step close to the
all-electric mine of the future. (Photo: Boliden
In April 2024, Boliden, Epiroc and ABB announced that they had successfully deployed the world’s first fully battery- electric, trolley truck system on an 800-m long underground test track with a 13% incline at Boliden’s Kristineberg operation in Sweden. The project was supported by funding from the Swedish innovation agency Vinnova Sustainable industry and will contribute to Boliden’s vision to become the most climate friendly metals provider in the world.

E&MJ joined the three partners in August for a tour of the test facility and to gain more insight into the project. “We are united in our commitment to sustainability,” Jérôme Cloué, vice president of electrification at Epiroc, said of the trio: “Our collaboration is essential in pushing the boundaries of what’s possible in electrification, and that’s exactly what we’ve done through this project.”

Designing a Safe, Productive System
The project began in 2021 with the aim of finding a zero-emission, wheel-based haulage solution for the Rävliden mine — a satellite orebody and extension of the Kristineberg mine located in the Boliden Area — which will, eventually, be a fully electric operation. At the time, no battery-electric trolley trucks or systems were commercially available (although there is a Kiruna truck installation running at a mine in Canada), and the mine faced the additional challenges of experiencing high humidity and dust levels, and highly acidic (pH 2) water ingress. To make their vision a reality, the teams worked together to design and build the necessary systems for both the truck and the mine, as well as define new vehicle interfaces and the necessary standards.

Similar to an open-pit trolley installation, the system powers the battery- electric mine truck when travelling fully loaded up-ramp and enables battery regeneration during drifting. ABB’s eMine Grid-to-Wheel solution provided the backbone for the electrical infrastructure, which includes on-truck hardware, such as the pantograph, motors and inverters, as well as catenary lines, rectifiers and substations for energy delivery in the mine. The substation for the test track was pre-manufactured and shipped to the site in a split container for easy transportation underground. It was configured with a 12-kV OHL switchgear and 1,500 volts-DC capable of powering a track up to 1,700-m in length. A 1.5-mega- Watt (MW) controlled rectifier was also selected, along with two 1.8-MW diode rectifiers, auxiliaries and interfaces.

The tunnels in which the vehicle operates are multipurpose, accommodating light vehicle traffic as well as haulage, and the cramped conditions meant that electrical and environmental safety were a big focus from day one. Insulation of the electrical components was key, as the dust that Kristineberg generates is conductive due to the presence of microscopic copper particles. ABB’s Strategic Account Manager for Boliden, Lars Brännstrom, explained that multiple control layers have been built into the system to ensure its safety and that, despite running it under the toughest conditions during testing e.g., 100% humidity, there were no insulation issues.

He added that regardless of whether a trolley system is designed for openpit or underground use, it’s vital that miners and their suppliers work together to fine tune system performance and understand the wider impacts of the trolley system on the operation. For example, he explained that during testing, road maintenance was found to be crucial in smoothing the truck ride and improving contact between the pantograph and the overhead lines.

Creating the MT42 SG Trolley Truck
For the truck, Epiroc adapted its proven MT42 S battery-electric model (42-metric- ton haulage capacity), equipping it with an ABB DC/DC converter, HES880 inverters and AMXE motors. The new prototype, dubbed the MT42 SG Trolley, has a 40% smaller battery than its predecessor with a new heating and cooling system, a pantograph (which has a similar design to that used on road trucks) plus control system, and voltage converters.


Swedish collaborators are proud to have successfully
deployed the first fully battery-electric trolley truck system.
(Photo: Boliden)
The trolley system is integrated with the ABB 800xA distributed control system (DCS) to allow for the future integration of automation, which Jonas Ranggård, program manager, electrification, for Boliden Mines, said was a key step to optimizing battery-electric fleets.

Anders Lindkvist, product manager for large minetrucks at Epiroc, who spearheaded the new truck design said that thanks to the lower wear rate, the battery on the MT42 SG Trolley is expected to last around 50% longer than that in the MT42 S — at least a full truck lifetime, or approximately 20,000 operating hours, depending upon the application. Currently, the new truck costs around 30% more than its predecessor, but Epiroc is working to lower this. The teams emphasized that it’s still early days for the system, but benefits thus far include an 80% reduction in heat compared to a diesel truck. CO2 emissions are reduced by 70% depending on the electrical source, and operating noise is greatly reduced.

Ventilation requirements are also lower compared to both diesel and battery-electric trucks that use static charging. For example, three MT42 S trucks require around 400-kW of ventilation per truck, plus 300-kW for ground ventilation — a total of 1,500-kW. In contrast, the MT42 SG Trolley doesn’t require any truck ventilation, so only 300-kW of ground ventilation is needed. In terms of production, the system does not need to stop for refueling, charging or battery swapping. When combined with automation, it can run 24/7, boosting simulated production (tons per hour) by 50% compared to a diesel fleet and 25% compared to a battery-electric fleet that uses static charging. Most of the moving parts (90%) have been eliminated from the truck design which significantly reduces its maintenance requirements, and the electric drivetrain provides a higher travel speed on ramps than both diesel and battery-electric trucks.

The Next Steps
During development, extensive simulations were used to optimize the test setup and predict the final requirements of Rävliden’s haulage system. This allowed Epiroc and ABB to help Boliden calculate its optimal fleet size and understand how best to build redundancy into the system. Following a year of testing, Boliden has given the greenlight to implement a full scale, 5-km long autonomous electric trolley system at Rävliden, and has placed an order for four Minetruck MT42 SG Trolley trucks from Epiroc, the production of which has already begun.

Going forward, the ABB-Epiroc designed trolley system is now commercially available for other operators to purchase, a number of whom were onsite to see the test track for themselves when E&MJ visited. The system is vendor agnostic which means that in the future, it could be used with compatible battery-powered vehicles from other manufacturers, although it can be rolled out immediately with an MT42 SG Trolley fleet.

The system is best suited to mines with long, straight haul ramps (although curves can be accommodated too), high productivity requirements and a long mine life (5+ years depending upon production). The drifts at the Kristineberg test site measure 6-m wide and 6-m high, but the system can be adapted for smaller tunnels too. Both brownfield and greenfield installations can be accommodated, although the teams pointed out that, at a greenfield application like Rävliden, the system would be easier to optimize.


Epiroc’s battery electric MT42 SG Trolley truck has been put through its paces on the
Boliden test ramp. (Photo: Boliden)
“Any truck that’s equipped with the trolley interface and has the correct electrical parameters can be connected to the system,” explained Nic Beutler, global eMine solutions manager at ABB. “We’re already seeing a move towards standardization in 2.6- kV open-pit trolley systems, where any truck that has the right pantograph, bandwidth, electrical components etc. can connect. We’re pre-empting that requirement underground too with our agnostic approach.”

Franck Boudreault, Underground Application Expert Electrification at Epiroc, added: “In the future, another piece of kit that could benefit from dynamic charging capabilities are graders. These vehicles spend a lot of time on the ramp and consume a lot of energy, so they could be the next followers.”

Go Together, Go Faster
Ultimately this project demonstrates the value, speed and ingenuity that collaboration can bring to mine electrification projects: the future is, quite literally, brighter for everyone, if companies can find ways to work together.

“No company can solve the challenge of climate change alone,” Ratna- Kanth Dittakavi, global eMine sales manager at ABB, summarized. “Collaborations not only accelerate our progress towards decarbonization, but also bring forward solutions, ideas and knowledge that companies might not have considered otherwise.

“It’s important that we all work together to define and create open, interoperable, agnostic solutions and standards, so that we can meet the needs of the energy transition. This project is an example of what we can achieve if we work together.”


As featured in Womp 2024 Vol 10 - www.womp-int.com