Browns Range Will Restart
Northern Minerals has commenced planning and logistics to support the restart of operations at the pilot plant, which will initially focus on testwork in the beneficiation circuit followed by tests in the hydrometallurgical circuit. The company will also proceed with the mechanical construction and installation of ore-sorting equipment at the front-end of the pilot plant.
Exploration activity across the Browns Range tenement package will also be ramped-up, with a budget of $4.5 million to $5 million being allocated for greenfields exploration, further evaluation of identified mineralization and to boost confidence in resources, with the objective of increasing the overall life-of-mine potential of the project, the company said.