EcoTails: A New Approach to Large
Scale Tailings Disposal
Co-mingling coarse material with wetter filtered tails could enable the cost-effective
construction of safer TSFs
By Steve Fiscor, Publisher & Editor-in-Chief
While TSFs have become a limiting factor for some operations, safety and environmental sustainability are also major engineering considerations. On average, over the last 30 years, TSFs have experienced 20 dam failures per decade and a third of them have been serious safety and environmental liabilities. Two regions in the Americas are still recovering from the most recent serious disasters: Mount Polley in British Columbia and Samarco in Brazil.
Many engineers believe the solution involves dry-stacked tailings (DST). The sticking point, however, is the term “dry.” Traditionally, tailings are transported as a slurry. Any effort to reduce that moisture adds a cost and reduces the effectiveness of the transporting process. On top of that, many mines are operating in arid locations where water is a valuable commodity in its own right.
A little more than three years ago, FLSmidth began looking at ways to improve the dewatering process. The initial fruit of those efforts was the Colossal automatic filter press. It uses high pressure and fast filtering to achieve much larger single machine capacity and optimal cake moisture concentration. It is capable of discharging 20,000 mt/d of filter cake and can recover 600 cubic meters per hour (m3/h) of process water in a relatively small footprint. A large mine with 150,000 mt/d of tailings would require seven to 10 Colossal filters depending on filtration characteristics.
While recovering process water on a massive scale is possible with a significant investment, FLSmidth and Goldcorp began to look for a solution that would provide a step-change for DST. They knew that allowing an increase in the moisture level of the filter cake would reduce the scale and cost of the dewatering solution. The challenge was to give the TSF the required strength that is needed when the higher cake moisture tailings are deposited. The solution was to use waste rock to add the needed strength. The mixing or co-mingling the filter cake with coarse materials on a continuous basis, gave birth to the EcoTails program.
Seeing the Need for a
Step Change
For many years, FLSmidth has been developing
machines to support tailings
solutions, such as paste thickeners, belt
presses, vacuum filters and filter presses.
“In 2014, we decided to build a really
large filter press — Colossal automatic filter
press, that is currently being installed
in South America,” said Todd Wisdom, director
of tailings for FLSmidth. “That was
a major achievement in the evolution of
filter presses.”
At about the same time, Wisdom recalled a conversation with a mining executive, who said he loved that filter, but commented it was too small. Wisdom reminded him it was twice the size of any filter press currently on the market. He said, “Yeah, I know, but we need something bigger and better.” At that point, the engineers at FLSmidth realized they needed a new approach.
As point of reference, Wisdom cited a mining operation with some clays in the deposit. To process 150,000 mt/d of filtered tailings, they would have needed 72 2-m x 2-m filter presses. “If you tell a mine they need 72 of anything, they are going to get squeamish,” Wisdom said. “You could cut that figure in half with 36 Colossal Filters, but that’s still a big proposition.”
The pressure filtration process is a batch operation. So, they started to look at reducing the steps of the batch process. That led to reducing the air blow in a filter for fast filtering with a wetter filter cake. “We could reduce that number by half again,” Wisdom said. “So we went from 72 filters to six or eight and that’s much more reasonable for them as far as operations and maintenance.”
Reducing the air blow increases moisture, which yields less geotechnical strength for the filtered tailings. “During the last six years or so, most mines were looking for filter cake with 13% to 16% moisture on a metallurgical basis,” Wisdom said. “To get to that level requires quite a bit of air blow. By increasing that figure to 18% to 20%, the filtration time can be reduced significantly, meaning more batches per hour and higher unit capacities. The problem is dealing with that wetter filter cake.”
Editor’s note: Metallurgical engineers and geotechnical engineers use a percentage figure to describe moisture differently. A metallurgical engineer uses a weight percentage, which is the weight of water over the total weight of the sample. The percentage used by geotechnical engineers is the weight of the water over the weight of the solids.
To counter the wetter filter cake, the EcoTails team proposed a method of mixing waste rock to add strength to the composite. Essentially, the EcoTails concept filters fast with less machines and adds strength by co-mingling it with waste rock. “We have trademarked two names: EcoTails, which is the project and process, and GeoWaste, which is the composite material — the comingled waste rock with the filtered tails,” Wisdom said.
Miners have been co-mingling materials forever, but they have mostly done it on a small scale with trucks and shovels to mix and move materials. That won’t work for 150,000 mt/d. Placing the material on a conveyor with some specially designed transfer chutes would work and, at the end of the process, a completely mixed material can be placed on the TSF. “Most conveyors are moving material at a velocity of 4 m/second (s) to 6 m/s so there is a fair amount of kinetic energy at the transfer point,” Wisdom said. “If the system is designed correctly, we can use that energy to mix the materials.”
The Advantages of a
Less Permeable Pile
In addition to strength, GeoWaste has other
advantages. By filling the voids in the waste
rock with filter cake, the permeability of the
waste rock pile will be greatly reduced. “The
coarse rock particles give the pile a higher
density, which provides quicker self-weight
consolidation, adding more strength more
quickly in the TSF,” Wisdom said.
From a safety perspective, the water on top of the TSF dam and the whole decanting process needs to be removed. On average, the mining industry experiences two TSF dam failures per year. It’s not the dam failure that causes the damage, however, it’s all the water behind the dam that fouls downstream waterways or worse. A dry-stacked TSF can still fail, it will only flow 100 m instead of 100 km. Additional storm water will not accumulate because of the low permeability; the water simply runs over the top.
The lower permeability could also have a long-term positive impact regarding ARD potential. “This won’t eliminate all ARD, but there are studies that say that if the saturation level of a pile is 85% or more, you can stop ARD, but we haven’t proven that yet,” Wisdom said.
Thickeners recover around 70% of the process water. The filter presses recover much of the rest. “EcoTails doesn’t remove any more water than traditional filtered tailings, but it can be applied to more mines economically,” Wisdom said. The filter cake does contain some water and the mine will need some type of collection point for storm water runoff, but there will not be much seepage because of the permeability of the pile is so low.
Justifying Costs
For a traditional TSF using a rock filled
dam, in general operating expenses are
estimated at $1.50/mt and the capital
expenses are $1/mt. Typically, the water
ratios are between 0.5 and 0.7. “What
we have determined, and we are in the
process of performing the pilot scale
testing and plant demonstrations to
prove this … with the generic EcoTails
case, we see operating expenses at $2/
mt and capital expenses $0.50/ton or
lower,” Wisdom said. “That puts this
solution on an even keel with traditional
systems over the life of a mine.
“Moreover, if the mining company is considering a 1-billion-ton reserve, they will be looking at $500 million in capital cost and $2 billion in operating expenses,” Wisdom said. “While those numbers are a bit staggering, we are going to prove that EcoTails is directly competitive on a total cost basis with conventional wet tailings. They cost the same, but GeoWaste presents less risk and recovers more water and that should be a winner in the marketplace.”
Again, the water savings are not any greater than traditional filtered tails, it will just make the process more applicable. The old rule of thumb for filtered tailings, Wisdom explained, was an all-in placed cost of $4/mt. “We are trying to cut that significantly,” Wisdom said.
Water costs are relative. In South America, water costs are estimated between $5/m3 and $7/m3. “If a 100,000- mt/d operation changes its water ratio from 0.7 to 0.17, which is what should happen when they switch from a traditional cyclone sand dam to a filtered tailings solution, the amount of makeup water that they would need decreases from 70,000 m3/day in the sand dam case to 17,000 m3/day,” Wisdom said. “That’s 53,000 m3/day in water savings. Over 10 years, that’s about 200 million m3 and, at $5/m3, that’s $1 billion in water savings.
“That’s a big number and when you combine that with being cost competitive and safer, it seems like a solution that will have some traction for the industry,” Wisdom said. More times than not, mining gets a bad rap due to these environmental mishaps. EcoTails could present an environmentally sustainable solution to increase productivity that’s economically and socially acceptable.