Oil Sands Producers Deal With
Financial Friction—and Fire
Canada’s oil sands industry has faced a number of challenges over the past 18
months, with political, environmental and market hurdles to overcome
By Simon Walker, European Editor
Political Changes
Up to May 2015, the Alberta provincial
government had been controlled by
conservative parties, with the Progressive
Conservatives having been in power
since 1971—almost the entire lifespan of
the oil sands industry. The picture then
changed with the center-left New Democratic
Party winning in 2015. Having
flagged its intentions later in the year, just
before the Paris climate-change summit,
in May the provincial government introduced
legislation covering the introduction
of a C$20 per metric ton (mt) carbon
tax across Alberta’s economy starting next
January. In addition, the government is
planning a new cap on oil sands carbon
emissions, which, it noted, account for
around one-quarter of the province’s 280
million mt annual total.
By way of explanation, the Alberta government noted that the province’s oil sands facilities are currently charged a Specified Gas Emitter Regulation levy based on each individual facility’s historical emissions, with no current limit on oil sands emissions, either by facility or industry-wide.
The new approach includes an oil sands-specific emission performance standard, whereby a C$30/mt carbon price will be applied to oil sands facilities based on results already achieved by high-performing facilities. This, the government said, will drive toward reduced emissions and carbon competitiveness, rather than rewarding past intensity levels.
In addition, there will be a legislated emissions limit on the oil sands of a maximum of 100 million mt in any year, the aim being to help drive technological progress and ensure the use of new technology that takes more carbon emissions out of every barrel of oil produced.
Meanwhile, Canada’s federal government is still in negotiations with the provinces over ways of implementing the promises made at last year’s Paris climate summit. A report in the Globe and Mail in June noted that “Canada faces a significant gap between emissions reductions that would result from current climate policies and what is needed to reduce emissions by 30% below 2005 levels by 2030, as promised in Paris. And Ottawa has pledged under the Paris accord to improve on that target.”
Keystone Stymied...
Stretching nearly 1,800 km (1,179
miles) from Hardisty, Alberta, to south
of Steele City, Nebraska, TransCanada
Corp.’s Keystone XL pipeline was, in the
company’s words, “intended to be a critical
infrastructure project for the energy
security of the United States and for
strengthening the American economy.”
After a seven-year review, during which time the project became more of a political and environmental football than a mere pipeline, President Barack Obama pulled the plug by refusing the presidential permit it needed. “America is now a global leader when it comes to taking serious action on climate change,” he said. “Frankly, approving that project would have undercut that global leadership, and that is the biggest risk we face: not acting.”
The Alberta government was less than impressed, but has used the rejection as leverage in its new policies. “We got a major wake-up call a few weeks ago in the form of a kick in the teeth from the government of the United States,” said Provincial Premier Rachel Notley. “Unfairly in my view, the president of the United States claimed that our production is some of the dirtiest oil in the world. That is the reputation that mistaken government policy in the past has earned for us.”
Having taken a C$2.9 billion writedown on its accounts over its investment to date, TransCanada then sought a negotiated settlement with the U.S. government— to no avail, and in June issued a $15 billion-plus claim for arbitration under the North American Free Trade Agreement (NAFTA).
Whether the company can achieve its aims under President-elect Donald Trump’s regime remains to be seen, and while he has signaled his willingness to reconsider the project, he has also made it very plain indeed that there would be a substantial quid-pro-quo involved in terms of long-term profit-sharing.
...While Northern Courier Nears Completion
Meanwhile, TransCanada is maintaining
progress with its Northern Courier pipeline,
designed to move heated bitumen
and diluents a distance of some 90 kilometers
(km) (56 miles) between the new
Fort Hills mine and bitumen-extraction
plant and Suncor’s East tank farm, 27 km
north of Fort McMurray. The system consists
of a 24-in. bitumen pipeline taking
output from Fort Hills, and a 12-in. pipeline
for returning diluent, diesel and synthetic
crude oil from the tank farm to the
mine. The company’s contract includes
the construction of tanks and pump stations
at both ends of the line.
One of the challenges faced during construction was taking the pipelines across the Athabasca River. Here, Trans- Canada turned to the specialist contractor, Michels Corp., which used horizontal directional drilling to install the lines beneath the river bed. With both pipes running in a single 42-in.-diameter sleeve, the 2,195-meter (m) or 1.36-mile bore was a new record for the company, as well as being the longest in North America for this diameter.
The initial pilot hole drilling and reaming was undertaken using two 1.2-million- lb rigs on each side of the river, with the casing then being pulled back from one side to the other through the hole. The final pipe pull took 36 hours to complete, with the company using 10 cranes, five side-booms and three excavators to support the pipe, which was in a complex horizontal curve. As it was being fed into the hole, the pipe reached a height of 14.3 m (47 ft) before being pulled under the river at a depth of more than 70 m (230 ft).
Suncor Bets Big for the Future
Seizing an opportunity when other players
blinked in the face of low oil prices
and uncertainty over future environmental
policy, over the past 12 months, Suncor
has consolidated its position as the
major producer in Alberta’s oil fields. Its
first foray into the acquisitions market, a
little more than a year ago, saw it buying
a 10% stake in the Fort Hills project
from its partner, Total E&P Canada. The
C$310 million purchase increased the
company’s holding in Fort Hills to 50.8%,
with Total retaining 29.2% and Teck Resources
maintaining its 20% stake.
And 2016 was not too old before Suncor was in the market again, first paying C$4.2 billion (plus the assumption of C$2.4 billion debt) for Canadian Oil Sands Ltd., then a further C$937 million for Murphy Oil’s 5% stake in Syncrude. Canadian Oil Sands was previously the largest single Syncrude shareholder with a near 37% stake, and the two acquisitions leapfrogged Suncor from a 12% position in Syncrude to holding 53.7% of the operation.
The company noted that its increased stake in Syncrude, and with Fort Hills and its Hebron project on target for first oil late next year, it expects to increase its output by more than 40% compared to 2015, and to achieve 800,000 bbl/d in 2019.
'The Beast'
Images of the wildfires that swept through
parts of the oil sands region and devastated
some Fort McMurray suburbs in early
May were broadcast worldwide, bringing
home to a global audience the terrifying
intensity of the flames. The mass evacuation
of the city and neighboring communities
added to the sense of utter impotence
in the face of the inferno.
Yet the whole incident passed with thankfully few casualties and, remarkably, very little physical damage to the oil sands industry’s mines, plants and infrastructure. Nexen reported that its Long Lake camp was burnt, although its in-situ wells and treatment plant remained intact. The fires reached the edge of Suncor’s Base Plant mine, the closest north of Fort McMurray, but then veered away. After the initial outbreak of the fires, but before the evacuation, several operations had already been forced to reduce output because of a shortage of diluents, the pipelines to the south having been shut down as a precaution. And that was not the only pipeline problem to affect producers; their restart was slowed because product pipelines had become clogged with partly solidified bitumen and had to be cleaned out before normal flow could resume.
As for the cost, initial estimates—released earlier this year—suggested that the industry had lost more than 30 million bbl in production during the outage, worth upward of C$1.5 billion. In terms of the physical damage, the Insurance Bureau of Canada estimated insured property damage at C$3.58 billion, more than twice the amount of Canada’s previous costliest natural disaster—the 2013 southern Alberta floods.
For the provincial government, the fires could not have come at a worse time. With its contingency funds running low in response to weak oil prices, the cut in oil sands output cost it C$495 million, pushing its 2016 budget deficit to C$10.9 billion.
The Oil Sands’ Vital Role in Canada’s Oil Production
According to statistics from the Canadian Association of Petroleum Producers (CAPP),
production from Alberta’s oil sands grew from 974,000 bbl/d in 2005 to 2.365 million bbl/d last year. Put into perspective, while oil sands output accounted for 39% of the country’s total oil production in 2005, by 2015, the proportion had grown to more than 61%, with in-situ production making up 57% of the output from oil sands.
Looking ahead, the CAPP estimates that oil sands output will reach 3.7 million bbl/d in 2030, with mined output rising from 1 million to 1.5 million bbl/d over the next 15 years while in-situ output will rise even more, from 1.3 million to 2.1 million bbl/d. However, there is a problem looming for the future in terms of transport capacity to move oil produced mainly in western Canada to markets in the east and over the U.S. border. In its annual forecast report, the CAPP noted that Canada’s pipeline network has the capacity to move about 4 million bbl/d (from all sources), which closely matched the 2015 average supply of 3.981 million bbl/d.
The CAPP estimates that the production of Canadian oil, before imported diluent is added, will rise to 4.9 million bbl/d in 2030, while total supply, including added diluent, will then be 5.5 million bbl/d. Hence the need for major new oil pipelines, the organization pointed out, with the oil sands industry remaining the primary driver for Canadian oil production growth.
Cutting Costs and Emissions
With in-situ production now firmly established as the leading source of bitumen from
the oil sands, operators are looking for ways to cut their production costs and the carbon
emissions generated from conventional steam-assisted gravity drainage (SAGD) recovery
systems. These use steam injected into the host horizon to reduce the viscosity
of the bitumen and allow it to flow down to gathering wells. However, steam production
is expensive and uses significant quantities of natural gas as the fuel.
Before putting it on the back burner last year in response to the low oil price, Cenovus Energy and ConocoPhillips anticipated that their Narrows Lake in-situ operation would be the first to commercially use solvent extraction with SAGD. Their process uses butane as the solvent, being added to the steam to dilute the bitumen and allow it to flow more easily. Benefits claimed include lower water and natural gas usage, and lower carbon emissions.
Meanwhile, Suncor and Nsolv Corp. have been trialing Nsolv technology at Suncor’s Devon in-situ test site since 2013, with the pilot plant having produced more than 100,000 bbl of heavy crude to date. The process also uses butane or propane as the solvent, but on its own with no need for steam. The heated solvent dissolves the bitumen, but leaves behind unwanted materials such as coke-forming asphaltenes, sulphur and heavy metals.
Nsolv claims that the process cuts energy requirements by up to 75%, greenhouse- gas emissions by 80% compared to SAGD, and uses no water. In September, the two companies agreed to continue working together to complete the pilot operation, and to evaluate the potential to advance the technology.