Norilsk Developing $1.1B Chita Copper Project
Capital expenditures to develop the Chita project are estimated at $1.1 billion. EBITDA margins are estimated at about 50%, with an asset IRR of about 30%. Mine life will be more than 30 years.
Chita project ore will be processed through a 10-million-mt/y concentrator to produce 66,000 mt/y of copper in concentrate, 3.1 million mt/y of magnetite concentrate, and 219,000 oz/y of gold in concentrate.
Infrastructure development includes construction of a new, approximately 600-km rail line, which is being financed 25% by Norilsk and 75% by the Investment Fund of the Russian Federation.