First Quantum Targeting 320,000 mt/y Copper at Cobre Panama
On the basis of the current resource estimate and planned initial installed throughput capacity of 70 million mt/y, Cobre Panama is now expected to produce an average of about 320,000 mt/y of copper on a life-of-mine basis, approximately 20% higher than in the Inmet plan. Average annual life-of-mine by-products production is estimated at 100,000 oz of gold, 1.8 million oz of silver, and 3,500 mt of molybdenum.
The 70-million-mt/y throughput target is approximately 17% higher than in the Inmet plan and applies to the first 10 years of a project life that is estimated at 34 years.
Project planning is based on estimated measured and indicated resources of 3,271 million mt, inclusive of reserves. Grades will average 0.5% total copper for the first 10 years and 0.37% for the remaining mine life. The average life-ofmine strip ratio is 0.7:1.
The re-engineered and larger Cobre Panama project is now scheduled for construction completion, commissioning, and first concentrate production in the second half of 2017.
Capital cost to develop the project is estimated at $6.4 billion, inclusive of $913 million incurred before First Quantum acquired of the project. Capital per installed metric ton of capacity is approximately $17,125.
Since acquiring the Cobre Panama project, First Quantum has transformed development from an out-sourced approach to a complete “in-house, self-perform” operation, with third-party engineers and contractors now utilized only for identified specific tasks. Significant quantities of on-site equipment have been purchased by First Quantum from contractors whose contracts have been either canceled or modified. First Quantum now fully controls all site development activities. Site accommodation, road access, and communications are now all fully functional.
The locations of key site infrastructure, including the processing facilities, were reviewed, and an alternate, more practical plant site was selected that is expected to be more cost effective to construct and allow for better access to the proposed inpit crushing and conveyor systems and the main access road.
The Cobre Panama project is located 120 km west of Panama City and 20 km from the Caribbean Sea coast. The concession consists of four zones totaling 13,600 ha. The project elevation is less than 300 m, but the topography features considerable local relief and is covered by dense rainforest.