First Majestic Starts Up at Del Toro
First Majestic also remains on schedule to double Del Toro mill throughput to 4,000 mt/d (2,000 mt/d flotation and 2,000 mt/d cyanidation) by the third quar-ter of 2014, when it will become the com-pany’s largest operation, producing 6 mil-lion oz/y of silver and significant amounts of lead and zinc.
Three underground mines—San Juan, Perseverancia/San Nicolas and Dolores— deliver ore to the Del Toro processing plant.
First Majestic has four other producing silver mines in Mexico: La Parrilla, San Martin, La Encantada and La Guitarra. Del Toro is located 60 km southeast of La Parrilla.
First Majestic produced 9.1 million sil-ver equivalent oz during 2012 (8.3 million oz of silver) and is forecasting production of 12.3 million to 13 million silver equiva-lent oz (11.1 million to 11.7 million oz of silver) during 2013.
First Majestic President and CEO Keith Neumeyer said, “The start-up of the Del Toro silver mine marks a very important milestone for First Majestic. This year, the company will celebrate its 10-year anniver-sary by breaking through 10 million oz of silver production as a result of Del Toro coming on stream.”