Three-Phase Mining Effluent Treatment Plant to Meet Stringent Standards
High-rate ballasted flocculation technology, cyanide oxidation and carbon adsorption
comprise an advanced, three-phase cyanide and metals removal system for a
Central American gold project
By Chris Howell and Dave Christophersen
The mill, which utilizes the Merrill- Crowe process, is designed to process more than 1.8 million dry metric tons (mt) of ore per year. Marlin produced 227,200 oz of gold and more than 2.8 million oz of silver in 2007, its second full year of production. The tailings and water generated from this facility are treated with an SO2 air cyanide removal technology prior to discharge to the mine’s tailings impoundment. The impoundment currently contains 4 million m3 of tailings and is expected to expand to nearly 20 million m3 by the end of the mine’s life.
Because the mine will likely need to discharge water from its tailings impoundment at some point in the future, Marlin is building a new water treatment plant exclusively for that purpose.
“We must be able to treat the water so it complies with both Guatemalan and World Bank discharge standards, in addition to a number of other stringent standards required by Goldcorp,” said Lisa Wade, environmental director for Goldcorp. In fact, Goldcorp has taken extra precautions beyond that which is legally required, by self-imposing additional stringent standards at the Marlin project.
To ensure this greater level of protection, Goldcorp complies with the International Cyanide Code and other more stringent requirements, including World Bank standards. For example, final effluent limits for the new water treatment plant include: 0.5 ppm WAD (weak acid dissociable) cyanide, 0.1 ppm free cyanide and 1 ppm total cyanide. There are also extremely lowlevel discharge limits for metals including mercury.
Crown Solutions, a business unit of Veolia Water Solutions & Technologies (VWS), was awarded the engineering, procurement and construction management contract for the cyanide oxidation and metals removal plant. The new system will be capable of treating water from Marlin’s tailings impoundment at a rate of 2,200 gal/min.
The treatment plant will have three specific phases of treatment: cyanide oxidation, clarification and carbon adsorption. These additional treatment steps will reduce the cyanide levels to meet the higher discharge standards adhered to by Goldcorp.
In order to meet final effluent limits for total, WAD and free cyanide, Crown Solutions determined, through lab treatability studies and on-site testing, that pH control and iron sludge adsorption, along with peroxide oxidation, copper sulphate catalysis and precipitation, would be the most effective treatment. Iron sludge adsorption and the addition of the heavy metal chelating agent was selected to remove primary Hg.
“We had different options for achieving an oxidation reaction to destroy the cyanide,” Wade said. “We looked at both sodium hypochlorite and hydrogen peroxide but were concerned with potential chloride buildup over time as well as other concerns with using sodium hypochlorite. We ran tests with both reagents and were very successful using hydrogen peroxide.”
Clarification Phase
The second treatment phase, clarification
to remove the metals and sediments,
will be carried out by Actiflo
high-rate, sand-ballasted flocculation
and settling technology.
In the sand-ballasted flocculation process, raw water is first mixed with a coagulant in a high-shear environment where it is retained for two minutes. In the next tank, the water is injected with a polymer along with microsand and mixed aggressively for roughly another two minutes. The water then enters a “maturation zone,” where gentle shear is applied for an additional six minutes.
The technology has proven both flexible and versatile. The coagulation phase works on the total suspended solids (TSS) and chemically active contaminants. The Hydrex flocculent ensures that the sand bonds strongly to the flocculated solids. The solids by themselves are typically at or near the density of water, so they cannot settle rapidly without the added weight of the microsand (2.65 specific gravity). Once weighted with the tiny sand particles, the flocs sink immediately in the settling tank.
The Actiflo process serves not only as an effective high-rate clarifier but also as a highly versatile chemical reaction vessel. Depending on pH conditions, colloidal and dissolved metals in the influent can be precipitated using classic and familiar chemical methods for efficient sand-ballasted removal in the settling step. Because retention times in the system are very rapid (minutes instead of hours), the technology is extremely compact, providing increased capacity without the large surface area requirements of traditional flocculation/sedimentation systems.
“The Actiflo system definitely caught our eye,” Wade said. “Clarification tanks are typically huge and you have this issue of where you’re going to put them. The Actiflo clarifier is a much smaller size tank, yet provides the same amount of clarification.” Actiflo systems are typically five to 20 times smaller than conventional clarification systems offering similar capacity.
The unit uses a portion of the filtered effluent to spray over the filters and backwash them as they are in the process of filtering effluent, thereby allowing for continuous operation as well as continuous cleaning. The compact design of the disc filter configuration provides two to three times more filter area compared with drum filters of the same external dimensions.
Carbon Adsorption Phase
The third and final treatment phase is
carbon adsorption. Here, water is
pumped through columns containing
activated carbon, accumulating substances
in the filter. The activated carbon
is supplied by PICA.
Through adsorption, the contaminant material physically attaches on the surface of active carbon in the mesopores and micro-pores of the active carbon. Depending on the mercury level and chemistry removal efficiencies, it may not be necessary to rely on carbon filters for secondary mercury treatment. But because Goldcorp wants to be absolutely certain that discharge at the mine meets its own stringent standards, it decided to include it as a contingency measure.
The new treatment plant was successfully commissioned during early 2009. Wade said the mine plans to remain flexible regarding its operation following start-up and commissioning.
“The most important aspect to this project is to have the treatment plant available. How much or how little we use it is something that will be decided based on multiple factors. We could decide to let the water stay in the tailing dam and continue to reuse it in the process plant,” Wade said. “Or, we may operate the new plant periodically, or seasonally. But to be conservative, the new plant is designed to run continuously for the life of the mine, if needed.”
Environmental Protection
The western highlands of Guatemala are
home to picturesque mountains, narrow
river ravines and pastoral plains. It is
also home to the country’s highest concentration
of indigenous people. With
the safety and well being of the land,
waters, and population in mind, Marlin
is committed to operating a safe and
environmentally sound mining operation.
“All of our mining operations obviously have to meet the standards of the country we’re operating in, but we also want our mines to meet the more strict international standards—especially if the country’s standards are not as stringent as we think they need to be,” Wade said. “We believe that simply complying with the legal requirements at Marlin wasn’t protective enough of the environment, and the new treatment plant will help ensure that we are.”
Chris Howell (chris.howell@veoliawater. com) is sales manager and Dave Christophersen (dave.christophersen@ veoliawater.com) is technical director for Veolia Water Solutions & Technologies (VWS). VWS offers a complete range of water and wastewater solutions including feasibility and compliance studies, advanced water and wastewater treatment technologies and turnkey installations.