Crowflight Commissioning Bucko Lake Mine
Commissioning of the Bucko Lake crushing plant was essentially complete and crushing of ore had begun. Mill commissioning had been underway since early September, and crushed ore was being stockpiled in preparation for mill startup. Production of concentrate was expected to begin during the second half of October.
Bucko Lake is designed to process 1,000 mt/d of ore and produce 11.1 million lb/y of nickel in concentrates. Exploration of the Bucko Lake and satellite deposits is ongoing and indicates potential for establishing reserves sufficient to support a production increase to 1,500 mt/d.