Tenke Fungurume Cu/Co Project Advances to Meet 2009 Production Startups


Lundin Mining Corp. recently issued an update on the $1.75-billion Tenke Fungurume copper/cobalt project in Katanga Province, Democratic Republic of Congo. Lundin holds a 24.75% interest in Tenke Fungurume. The majority interest (57.75%) is held by by operating partner Freeport-McMoRan Copper & Gold. Upon completion of the first phase of development, the mine is expected to produce about 115,000 mt/y of copper cathode and 8,000 mt/y cobalt. First production is forecast in the second half of 2009.

According to Lundin, the copper and cobalt hydroxide plant design and procurement is substantially complete, while cobalt refinery and acid plant design and procurement are under way. Construction progress has increased over the last several months since the end of the rainy season, aided by additional construction and logistics management brought in by Freeport from various global mining projects.

Tailings embankment construction, concrete installation, structural steel, process tank and pipe rack erection are advanced. SAG mill components, mixersettler cells, and other equipment and bulk materials are on site in anticipation of mechanical equipment and piping installation commencing in August.

The project's construction and operations work force includes more than 4,500 workers, most of which are Congolese. More than 100 Congolese employees have undergone training at various Freeport global mining operations and are being mobilized to site for construction assistance and pre-production activities.

Lundin said that pre-stripping of the Kwatebala deposit is enabling high grade ore stockpiling to support a rapid plant startup. Last September the project began using a continuous miner in a firstever application for sedimentary-hosted copper mining. This miner eliminates the need for traditional blasting and crushing of the ore and provides for highly selective mining of high-grade material. Lundin said the continuous miner has met and exceeded performance expectations and a second unit has been ordered.

In late June, supported by results from site exploration and ongoing Freeport process test work, meetings were held on major expansion planning. A series of mine expansion objectives is evolving and studies are advancing for the first phase of oxide plant expansion with construction to potentially commence immediately upon initial operations startup next year.


As featured in Womp 08 Vol 6 - www.womp-int.com