Dolores Headed for Third-Quarter Start
Dolores is an 18,000-mt/d operation designed to produce more
than 200,000
gold-equivalent oz/y over an initial
mine life of 15 years.
Minefinders Corp. has its Dolores openpit,
heap-leach, gold-silver project in
Chihuahua, Mexico, on schedule and
budget to begin mine production during
the second quarter and gold production
during the third quarter of 2007. The
18,000-mt/d mine is expected to produce
more than 200,000 gold-equivalent
oz/y over an initial mine life of 15 years.
Capital cost to complete the project is
estimated at $132 million.
During 2007, a resource expansion
program at Dolores is focusing on potential
mineable underground high-grade
zones below the current pit bottom and
on mineralized zones in peripheral structures
outside the current pit design.
Minefinders continues to look for ways to
optimize the project, including refinements
in mine planning and processing
that might derive from the new open-pit
resource and reserve estimates and from
possible future underground operations.
Additional 2007 development plans
include completion of a feasibility study
for a flotation mill to process high-grade
ores from the pit, expected to be added
in the third year of open-pit mine life,
with capacity for expansion to process
possible underground resources.
The primary mine equipment fleet
includes 15 Komatsu HD785 100-mt
haul trucks and two HD785 water trucks;
two Komatsu D375A, one D61, and one
D155AX dozers; two Komatsu PC3000
shovels; and two Komatsu WA900 and
one WA600 loaders. Ancillary equipment
includes a 60-ton crane, a WA470 tire
handler, three Bobcat loaders, a fuel
truck, and three graders.
A Nordberg C160 jaw crusher and four
Nordberg HP800 cone crushers constitute
the primary equipment in the crushing
plant. Power will be generated by six 1.8-
MW primary generators, as well as seven
other generators of various sizes. Gold will
be recovered at a Merrill-Crowe plant
designed and constructed by Lyntek.
Dolores site construction is being
managed by Minefinder’s Mexican operating
subsidiary and Ausenco Americas.
Terra Nova Technologies designed and is
building the crusher and the conveying
and stacking facilities. Rosales Construction
is handling the earthworks, and
ICSA is building the leach pad.