Galore Creek Receives Environmental Certificate
NovaGold reported in late February that
its Galore Creek copper-gold-silver project
in northwestern British Columbia
had received its Environmental Assessment
Certificate (EAC) from the provincial
government. Receipt of the certificate
cleared the way for issuance of the
various permits and authorizations
required to construct and operate the
mine. NovaGold anticipates that these
permits and authorizations will be issued
during the second quarter of 2007 and
that project construction can begin by
mid-year. Start of production is currently
scheduled for early 2011.
In this photo taken in mid-February 2007, construction crews were almost ready to pour
concrete for the ball mill
piers at Novagold’s Rock Creek project.
Galore Creek is located 150 km
northeast of Stewart, British Columbia,
where a year-round port is available for
shipping the project’s concentrates.
Average annual production during the
mine’s first five years of operation is
forecast at more than 432 million lb of
copper, 341,000 oz of gold, and 4 million
oz of silver in concentrates at total
cash costs of $0.38/lb of copper net of
precious metals credits. Overall life-ofmine
production is projected to average
23.7 million mt/y of ore for 22 years,
yielding an estimated average annual
production of 262 million lb of copper,
165,000 oz of gold, and 2.7 million oz
of silver in concentrates at total cash
costs of $0.62/lb of copper net of precious
metals credits.
The final feasibility study for Galore
Creek, completed by Hatch Ltd. in
October 2006, estimates the project’s
proven and probable reserves at 6.6 billion
lb of copper, 5.3 million oz of gold,
and 92.6 million oz of silver. Capital cost
to develop the project is estimated at
$1.74 billion, not including debt service
and expenses related to financing.
The EAC for Galore Creek contains a
series of commitments that NovaGold
will implement throughout the various
phases of the project. These include
ongoing assessment of water treatment
options; maintaining aquatic, fisheries,
and wildlife monitoring programs; continuing
the collection and analysis of
water, sediment, and biota; developing a
long-term maintenance and mitigation
strategy for the tailings impoundment
dam and spillway; and developing a
wildlife mitigation and monitoring plan
to identify measures to further reduce
effects on wildlife.
In February 2006, NovaGold entered
into a comprehensive agreement with the
Tahltan First Nation concerning development
of the Galore Creek project. The
agreement supports the Tahltan Nation’s
principles of environmental stewardship,
economic sustainability, and self-determination
and ensures collaboration
throughout the environmental review and
permitting process.
Rock Creek Update: On March 1, 2007, NovaGold reported that the
U.S. Army Corps of Engineers would reinstate the wetlands permit for NovaGold’s
Rock Creek project near Nome, Alaska. The permit was suspended in December 2006
pending review, following a lawsuit against the Corps challenging the Corps’ issuance
of the Clean Water Act wetlands permit for Rock Creek. The lawsuit alleged that
the Corps issued the permit in violation of governing legislation.
The Corps completed
an extensive review of the permitting process and concluded that the permit was
consistent with applicable laws and regulations. Accordingly, the Corps filed
notice of its intention to reinstate a modified permit on March 13. The modified
permit includes additional stipulations that cover reporting and mitigation.
Construction
at Rock Creek continued throughout the winter in upland areas and areas previously
disturbed. Work at the plant site proceeded on schedule. However, NovaGold anticipates
that the wetlands permit may be challenged again and that construction may be
impeded if the court enters an order in the litigation temporarily or permanently
enjoining the project. Should the permit be challenged, NovaGold will again support
the Army Corps of Engineers and ask to intervene in the lawsuit.
The Rock Creek
project is located seven miles from Nome on 14,000 acres of patented private land
owned 100% by NovaGold and 20,000 acres of land owned by the Bering Straits and
Sitnasuak Native Corporations. The mine is being developed as a 7,000-mt/d conventional
open-pit, year-round operation, producing 100,000 oz/y of gold at estimated total
cash costs of $260 to $285.