SAG Mill Success—Start with the Basics
New products and techniques proliferate for maintaining and improving mill
performance,
but careful planning at installation may be the most effective tool of all
SAG mills are often flexible enough to accomplish the same
size reduction provided
by two or three stages of crushing and screening, a
rod mill, and some or all of the
work of a ball mill.
With units available in ratings up to 35,000 hp, capable of supporting
a grinding line that can output more than 100,000 mt/d, SAG mills have played
a steadily growing role in mineral processing. To get an idea of the extent to
which this technology has been accepted by the mining industry, it’s only
necessary to look at a brief sampling of recent contract awards from major mill
suppliers.
• FFE Minerals Brazil was awarded a contract to supply a 26 x 16-ft, 6,500-hp
SAG mill—as well as a 21 x 32.5-ft, 9,600–hp ball mill—for CVRD’s
Paragominas bauxite mine in northern Brazil.
• Metso Minerals provided a 5,400-kW SAG mill along with technical services,
spare parts and supervisory services for erection and commissioning to Kunming
Iron and Steel Group Co. Ltd (KISCO) for its Dahongshan mine in Yunnan province,
China. Delivery was completed in the second quarter of 2006. Metso Minerals more
recently announced that it will supply grinding and flotation equipment to the
Gaisky copper mine of Ural Mining and Metallurgical Co. The order, valued at more
than €20 million, will be completed by the end of 2007 and comprises two
5,000 kW SAG mills, two 4,100-kW ball mills and 17 RCS (Reactor Cell System) flotation
cells, complemented by installation and commissioning support services.
• Wedgetail Exploration purchased a SAG mill from Thyssen Krupp Engineering
Polysius Division for installation at its Nullagine gold project in Western Australia.
The mill, which measures 6.1 m in diameter by 7 m long, is powered by a 3,500-kW
drive.
• Outokumpu Technology was selected to provide a 32-ft-diameter, 20-ft-long
SAG mill with 12,000 kW of installed power to First Quantum Minerals’ Frontier
project in the Democratic Republic of Congo. The trunnion-supported mill features
variable speed capability, allowing greater production flexibility and the ability
to cope efficiently with large ore variations. The Frontier mill is notable because
it highlights an approach toward over-coming what may be SAG technology’s
major challenge—load stabilization and control. A credible argument can
be made that the flexibility offered by SAG mills may also be their greatest weakness:
A mill that is touted to be capable of grinding anything that is fed to it, might
therefore be fed a mix of everything—ranging from vastly different chunk
sizes to variable
rock hardness. Feed variations such as this, as well as over or underloading a
mill, can result in less-than-optimum performance and make it difficult to achieve
satisfactory mill control. In fact, at least in part because of the attention
that must be given to the care and feeding of SAG mills, producers have begun
to look increasingly favorably at highpressure grinding rolls as a viable option
for grinding circuit design, either in combination with SAG mills or as a replacement,
particularly when dealing with lowgrade, abrasive ore. There are a number of laboratory
and software tools that can provide both preand post-installation solutions to
SAG mill power and feed problems. As an example, Dawson Metallurgical Laboratories,
based in Salt Lake City, Utah, USA, in association with the SAG Design Consulting
Group, offers SAGDESIGN test work and consulting. The SAGDESIGN test is performed
with a specially designed laboratory SAG mill and uses 7- to 9-kg (depending on
ore specific gravity) of –38 mm ore. The SAG product is then used as feed
to a Bond ball mill work index test. The results can be used to determine or confirm
SAG (or AG) and ball mill energy requirements. Other engineering and laboratory
firms offer similar services.
Variable Drive = Mill Efficiency
According to Outokumpu Technology, the advanced technology utilized in the Frontier
mill’s Hyper SER Drive ensures that the mill can operate efficiently both
above and below the synchronous speed of the motor, thus allowing better management
of variable feed rate and feed competency. The design also is claimed to facilitate
optimized handling of any short- or long-term variations in ore. Variable speed
offers optimized trajectory for the charge during mill operation, minimizing unnecessary
wear of the mill lining, according to Oskar Gustavson, Outokumpu Technology’s
global technology manager for grinding. “The beauty of this customized system
is that it is designed for optimal operation and can cope with pretty much anything.
This is critical, especially at remote sites which can be prey to challenging
situations such as voltage variations and thus unavoidable downtime. The Hyper
SER Drive can transfer to fixed speed mode during under-voltages, then transfer
back to variable speed when the supply voltage stabilizes, ensuring no costly
mill stops occur.” SAG mill breakdowns are costly events for producers.
As an example, early in 2006, Cia. Minera Doña Ines de Collahuasi had to
make temporary repairs on the drive on the largest and newest of its three SAG
mills at the Collahuasi copper mine in northern Chile, and then in mid-January
2007, finally began full replacement of the motor stator on the 21-MW gearless
drive for the 40-ft-diameter mill. The company expected the mill to be out of
action for approximately 65 days, representing about 30,000 mt of lost output.
The need to monitor and control these mills has led to the growth of a significant
sub-sector in mineral processing technology and product development.
Metso Minerals helped Anglo American’s Lisheen mine improve
mill uptime by developing
SAG mill linings that can be replaced without halting
production.
For example, the technical program for SAG 2006--the 4th International Conference
on Autogenous and Semiautogenous Grinding, held in Vancouver, B.C., in September
2006, listed roughly 100 papers devoted to research, product development, maintenance
and operation of this type of grinding equipment. Products for the care and feeding
of SAG mills range from preventive maintenance- oriented items such as Eriez Manufacturing
Co.’s SAG mill ball separator, which employs magnets to remove worn/broken
media from mills before thetramp iron can cause problems downstream; to real-time
monitoring devices such as Metso Minerals’ Electric Ear, which listens to
the sound level generated by a SAG mill and provides an indication of load conditions
within the mill. The Electric Ear can warn the operator of a low load level that
might result in liner damage, or an overload condition that could interrupt production.
Facing the risk of losing a significant amount of production in case of mill failure
or downtime, producers are constantly on the lookout for new products and methods
that have the potential for improving mill reliability and availability. Metso
Minerals, for example, helped Anglo American’s Lisheen mine in Ireland improve
mill uptime by developing SAG mill linings that can be replacedwithout halting
production of zinc and lead concentrates (E&MJ, “Sectional Mill Lining
Helps Keep Lisheen at Full Production,” Sept. 2006). The resulting design,
according to Metso, provides optimum performance while enabling the linings to
be quickly replaced during scheduled shutdowns. Lisheen opened in 1999 and produces
some 300,000 mt/y of zinc concentrates and 40,000 mt/y of lead concentrates. Material
is crushed underground, stockpiled and then conveyed to a 6.1 x 4.1-m SAG mill.
It is powered by a 2.3-MW motor and runs with 8%-12% of the mill’s volume
filled with 125-mmdiameter steel grinding balls. Incoming ore varies in zinc and
lead levels and hardness. The SAG mill therefore operates at variable speeds.
Normally, it would take about 60 hours to replace the mill’s entire lining
in a single job—too long for a monthly shutdown. A cooperative effort between
Metso and a mine task group was able to develop an approach that optimizes the
life of the linings and staggers the work so that replacement of the feed, central
and discharge sections of the mill’s liner are timed so that they need replacing
in different months. End sections take about 15 hours to fit while the central
section takes 36. Maximum life is gained from each section by monitoring the rate
of wear and carrying out the replacement only when it becomes necessary. As mills
grow larger, so do their support components. To illustrate, Eaton Corp.’s
Airflex division recently developed what is claimed to be the world’s largest
air activated drum-style clutch for use with grinding mills. The Airflex 76VC
measures 8 ft (2.4 m) in diameter and is capable of transmitting 7.3 million lb-in.
of torque with 9,500 hp at 200 rpm. Three of the units were shipped to a Newmont
Gold project near Battle Mountain, Nevada, USA, with another order in the works
for a customer in Chile Johnson Industries, which has offices in Canada and the
U.K., says its TL series toggle lever caliper brakes are the largest known spring
applied, hydraulic released caliper brakes in the world and are well-suited to
accommodate very high braking torque requirements in applications such as SAG
or ball mill installations. Features include a stackable design allowing 1 to
4 calipers to be mounted in a common frame and spring force compensation by toggle
mechanism resulting in constant braking torque. Caliper shoes are attached with
stainless steel shoe pins that incorporate countersunk lubricating holes, tapped
pin-pulling holes, and a pin retention groove. Caliper levers incorporate a unique
toggle mechanism to compensate for spring force and ensure constant braking torque.
The system is powered by a hydraulic power unit incorporating a manifold fitted
with valves to accommodate brake set, creeping and inching modes.
The Airflex 76VC drum-style clutch was designed to
handle the largest grinding mills currently available.
Focusing on Installation
With all the tools available for optimizing SAG mill performance, it might be
possible to overlook what could be the most important element of all in achieving
successful long-term performance: a careful, accurate and well-planned installation
sequence. The trend toward installation of large, gearless drive mills amplifies
the importance of this operation. At SAG 2001, Doug Farnell and Stephen Thompson,
both principals in Farnell-Thompson Applied Technologies, Montreal, Canada, presented
a paper titled Coordination of Mill, Motor and Plant Engineering for Large Gearless
Mill Projects. In their words, “The successful execution of a gearless drive
mill project requires that the mill vendor, motor vendor and plant engineer coordinate
their design efforts to a much greater degree than has been the case for most
traditional grinding mill projects. This coordination is critical to the design
of the three major elements of the system—the mill, the motor and the foundation—so
as to end up with a system that can be assembled, commissioned, and operated with
as few surprises as possible.” The authors divide the necessary tasks into
three main categories— basic design, operating and control logic design,
and installation coordination— and focus mainly on basic design elements
such as coordination of interfacing geometry/layout; structural design/analysis
of mill, motor and foundation; static and dynamic stability analysis of the overall
system; and coordination of services such as water, oil, air and power. Although
they recommend against assigning technical responsibility for overall design of
the motor, mill and foundation to any one specific entity, they do offer specific
guidelines for improving the technical coordination required to achieve a successful
installation. These include:
• Joint review by mill and motor supplier of foundation requirements, maintenance
access and clearances, and installation planning prior to submission to the project
engineer;
• Early exchange of data between mill and motor suppliers so that foundation
drawings from both reflect the same geometry;
• Improving the timeliness of the system studies such that there is the
opportunity to make any necessary design changes prior to fabrication;
• “Closing the loop” involving the mill vendor, motor vendor,
plant engineer, and owner on control logic implementation through joint review
of the final PLC logic; and
• Improved planning of the installation sequence, particularly in the area
of motor alignment vs. bearing adjustment so as to avoid repeating any tasks.